Portfolio

TRACK RECORD

wdt_ID Company Size Technology Project Status
1 Northlands Energy 63.36kWp Poly Si, roof mounted, grid tied. EPC Under construction. Commissioning December 2018
2 FNB-Kent 506.88kWp Poly Si, roof mounted, grid tied. EPC Under construction. Commissioning February 2019
3 FNB-Bank City 380.16kWp Poly Si, roof mounted, grid tied. EPC Under construction. Commissioning February 2019
4 FNB-Menlyn 126.72kWp Poly Si, roof mounted, grid tied. EPC Under construction. Commissioning December 2018
5 Nedbank 328kWp Poly Si, Carport/roof mounted, grid tied. EPC Under construction. Commissioning January 2019
6 HeliosRE 266kWp Poly Si, roof mounted, grid tied. EPC Under construction. Commissioning March 2019
7 PnP-Kraaifontein(HeliosRE) 184kWp Poly Si, roof mounted, grid tied. EPC Commissioned October 2018
8 Liberty(LLC & Parkade) 566kWp Poly Si, roof mounted, grid tied. EPC Under construction. Commissioning October 2018
9 Multichoice Samrand 226kWp Poly Si Carport, grid tied. EPC Commissioned May 2018
10 BMW Bloemfontein 120kWp Poly Si, roof mounted, grid tied. EPC Commissioned May 2018
Company Size Technology Project Status

TOP PROJECTS